Recommendations from the Autorité de Régulation des Télécommunications (ART) for access to the local loop and its operational implementation / 30 October 2000 Annex 3: Co-location initialisation process On receipt of a first intent to order together with a refundable deposit, France Télécom issues a quote for the construction of a room in standard dimensions as set out below. This quote is returned 15 days after receipt of the order to the various operators that forwarded an intent to order on the site by indicating the number of operators interested. Once the quote is accepted by one of the operators, France Télécom starts the work and delivers within four (4) months. On delivery, the price for setting up the room oriented towards the corresponding costs is divided by the number of operators who had accepted the order, depending on the number of bays delivered to each operator. If, at the time of delivery of the room, the amount of requests cannot be met, the escalation procedure set out above is implemented under the authority of ART. A system has to be designed whereby operators that subsequently enter the room are to refund the operators already in the room. The dimensions of the room to be built are calculated as follows:
|
![]() |